A low mechanical bid excludes controls wiring that is shown in the specifications, while the next bid includes it. How should the estimator handle the low bid before carrying it?

Correct Answer

C) Level the bid by adding or otherwise covering the missing controls scope

A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried. Other choices leave a known scope hole or distort all bids to match the omission.

Answer Options
A
Carry it unchanged because low number always wins
B
The estimator should delete controls wiring from all bidders
C
Level the bid by adding or otherwise covering the missing controls scope
D
The estimator should wait until commissioning to identify the gap

Why This Is the Correct Answer

A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried. Other choices leave a known scope hole or distort all bids to match the omission.

Why the Other Options Are Wrong

Option A: Carry it unchanged because low number always wins

Choice A gives Carry it unchanged because low number always wins. Its specific error: the option does not produce the required Bid qualification outcome, Level the bid by adding or otherwise covering the missing controls scope.

Option B: The estimator should delete controls wiring from all bidders

Choice B (Delete controls wiring from all bidders) is rejected because it treats Bid qualification as optional.

Option D: The estimator should wait until commissioning to identify the gap

The trap in D is Wait until commissioning to identify the gap. That selection is wrong because it tries to bypass the Bid qualification checkpoint.

Memory Technique

Picture a switch on the jobsite; bid qualification is solved by the action that leads to Level the bid by adding or otherwise covering the missing controls scope.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Bid leveling and scope qualifications" to confirm that A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.