A low mechanical bid excludes controls wiring that is shown in the specifications, while the next bid includes it. How should the estimator handle the low bid before carrying it?
Correct Answer
C) Level the bid by adding or otherwise covering the missing controls scope
A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried. Other choices leave a known scope hole or distort all bids to match the omission.
Why This Is the Correct Answer
A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried. Other choices leave a known scope hole or distort all bids to match the omission.
Why the Other Options Are Wrong
Option A: Carry it unchanged because low number always wins
Choice A gives Carry it unchanged because low number always wins. Its specific error: the option does not produce the required Bid qualification outcome, Level the bid by adding or otherwise covering the missing controls scope.
Option B: The estimator should delete controls wiring from all bidders
Choice B (Delete controls wiring from all bidders) is rejected because it treats Bid qualification as optional.
Option D: The estimator should wait until commissioning to identify the gap
The trap in D is Wait until commissioning to identify the gap. That selection is wrong because it tries to bypass the Bid qualification checkpoint.
Memory Technique
Picture a switch on the jobsite; bid qualification is solved by the action that leads to Level the bid by adding or otherwise covering the missing controls scope.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Bid leveling and scope qualifications" to confirm that A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass