NASCLAProcurement and Contracting Requirementsmedium

A low mechanical bid excludes controls wiring that is shown in the specifications, while the next bid includes it. How should the estimator handle the low bid before carrying it?

Correct Answer

C) Level the bid by adding or otherwise covering the missing controls scope

A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried. Other choices leave a known scope hole or distort all bids to match the omission.

Answer Options
A
Carry it unchanged because low number always wins
B
The estimator should delete controls wiring from all bidders
C
Level the bid by adding or otherwise covering the missing controls scope
D
The estimator should wait until commissioning to identify the gap

Why This Is the Correct Answer

A qualified bid with a missing required scope must be leveled or the gap must be covered before it is carried. Other choices leave a known scope hole or distort all bids to match the omission.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.