A GMP contract splits savings 60 percent to the owner and 40 percent to the contractor. Final cost is $120,000 below the GMP. What contractor savings share is earned?

Correct Answer

C) $48,000

The contractor share is $120,000 x 40% = $48,000. Other choices use a 50/50 split, the owner share, or the full savings.

Answer Options
A
$60,000
B
$72,000
C
$48,000
D
$120,000

Why This Is the Correct Answer

The contractor share is $120,000 x 40% = $48,000. Other choices use a 50/50 split, the owner share, or the full savings.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.