NASCLAProcurement and Contracting Requirementsmedium

A custom air-handling unit cannot be released until the submittal is approved. Which sequence should the procurement log reflect?

Correct Answer

A) Submit, review/approve, release, fabricate, ship, deliver

Long-lead procurement usually follows submit, review/approve, release, fabricate, ship, and deliver. Other choices put delivery, shipment, or release before required approval.

Answer Options
A
Submit, review/approve, release, fabricate, ship, deliver
B
Ship, fabricate, submit, approve, release, deliver
C
Deliver, approve, release, fabricate, submit, ship
D
Release, deliver, submit, fabricate, approve, ship

Why This Is the Correct Answer

Long-lead procurement usually follows submit, review/approve, release, fabricate, ship, and deliver. Other choices put delivery, shipment, or release before required approval.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.