A subcontract contains a clause limiting compensation for owner-caused delay to time extension only. What risk does the subcontractor need to recognize?
Correct Answer
B) The clause may bar delay-cost recovery while allowing more time, subject to enforceability
A no-damage-for-delay clause may limit the remedy for delay to additional time rather than delay cost, subject to contract language and enforceability. Other choices invent effects unrelated to the clause.
Why This Is the Correct Answer
A no-damage-for-delay clause may limit the remedy for delay to additional time rather than delay cost, subject to contract language and enforceability. Other choices invent effects unrelated to the clause.
Why the Other Options Are Wrong
Option A: The clause automatically adds profit to every delay
In procurement and contracting, The clause automatically adds profit to every delay is the wrong selection for No-damage-for-delay risk: the choice would not get the project to The clause may bar delay-cost recovery while allowing more time, subject to enforceability, which is the No-damage-for-delay risk result verified by the source.
Option C: Select the clause eliminates schedule updates for no-damage-for-delay risk
Choice C gives The clause eliminates schedule updates. Its specific error: it treats No-damage-for-delay risk as optional.
Option D: The clause turns the subcontract into unit-price work
Choice D (The clause turns the subcontract into unit-price work) is rejected because it answers the No-damage-for-delay risk prompt with the wrong practical move.
Memory Technique
Make no-damage-for-delay risk a tabbed card: cite the exact condition, then choose The clause may bar delay-cost recovery while allowing more time, subject to enforceability.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - liquidated damages / delay / claim notice to confirm that A no-damage-for-delay clause may limit the remedy for delay to additional time rather than delay cost, subject to contract language and enforceability.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
