The agreement states a fixed dollar amount per day for late substantial completion. What is the purpose of that clause?
Correct Answer
C) To establish agreed damages for delay when actual damages are difficult to determine
Liquidated damages establish an agreed amount for delay damages when actual damages are difficult to measure, provided the clause is enforceable under the contract and law. Other choices confuse damages with bonds, cost reimbursement, or time-extension approval.
Why This Is the Correct Answer
Liquidated damages establish an agreed amount for delay damages when actual damages are difficult to measure, provided the clause is enforceable under the contract and law. Other choices confuse damages with bonds, cost reimbursement, or time-extension approval.
Why the Other Options Are Wrong
Option A: Use liquidated damages to reimburse every actual cost without limit
Choice A (To reimburse every actual cost without limit) is rejected because the action skips the timing, documentation, or field-control step needed for Liquidated damages.
Option B: Use liquidated damages to replace the performance bond and treat the neighboring item as controlling liquidated damages
In procurement and contracting, To replace the performance bond is the wrong selection for Liquidated damages: the option tries to substitute, waive, or delete the Liquidated damages control; the item instead requires To establish agreed damages for delay when actual damages are difficult to determine.
Option D: Use liquidated damages to approve all time extensions automatically
Choice D gives To approve all time extensions automatically. Its specific error: it answers the Liquidated damages prompt with the wrong practical move.
Memory Technique
File liquidated damages under a closeout folder: condition first, number or duty second, answer To establish agreed damages for delay when actual damages are difficult to determine.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Liquidated damages" to confirm that Liquidated damages establish an agreed amount for delay damages when actual damages are difficult to measure, provided the clause is enforceable under the contract and law.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
