The contract states that contract time starts on the date named in the owner's written notice. Which document normally starts that time count?
Correct Answer
C) Notice to proceed
A notice to proceed commonly authorizes work to start and establishes the start of contract time when the contract says so. Other choices are procurement, closeout, or warranty documents.
Why This Is the Correct Answer
A notice to proceed commonly authorizes work to start and establishes the start of contract time when the contract says so. Other choices are procurement, closeout, or warranty documents.
Why the Other Options Are Wrong
Option A: Subcontractor quote
Choice A (Subcontractor quote) is rejected because the choice would not get the project to Notice to proceed, which is the Notice to proceed result verified by the source. The cited answer is Notice to proceed.
Option B: Accept the price information as submitted and leave notice to proceed unverified
In procurement and contracting, Punch-list memo is the wrong selection for Notice to proceed: the option does not produce the required Notice to proceed outcome, Notice to proceed.
Option D: Warranty certificate
Choice D gives Warranty certificate. Its specific error: it answers the Notice to proceed prompt with the wrong practical move.
Memory Technique
Make notice to proceed a tabbed card: cite the exact condition, then choose Notice to proceed.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Notice to proceed and contract time" to confirm that A notice to proceed commonly authorizes work to start and establishes the start of contract time when the contract says so.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
