The owner requires a bond that responds if the contractor defaults in completing the contract work. Which bond is that?
Correct Answer
A) Performance bond
A performance bond protects the owner against contractor failure to perform the contract. Other choices concern bid commitment, payment to claimants, or post-completion obligations.
Why This Is the Correct Answer
A performance bond protects the owner against contractor failure to perform the contract. Other choices concern bid commitment, payment to claimants, or post-completion obligations.
Why the Other Options Are Wrong
Option B: Bid bond
Choice B gives Bid bond. Its specific error: the option answers a paperwork, payment, or bonding issue.
Option C: Payment bond
Choice C (Payment bond) is rejected because it shifts the question into contract administration money flow.
Option D: Maintenance bond only
In procurement and contracting, Maintenance bond only is the wrong selection for Performance bond: the option delays or omits the controlling step.
Memory Technique
Treat performance bond like a labeled shelf; only the matching condition belongs with Performance bond.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Performance bond purpose" to confirm that A performance bond protects the owner against contractor failure to perform the contract.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
