A small emergency repair is authorized on a time-and-material basis. Which documentation is central to pricing the work?
Correct Answer
D) Agreed labor rates, material costs, equipment rates, and signed daily tickets or records
Time-and-material work is priced from agreed rates and documented labor, material, and equipment records. Other choices omit the records needed to support payment.
Why This Is the Correct Answer
Time-and-material work is priced from agreed rates and documented labor, material, and equipment records. Other choices omit the records needed to support payment.
Why the Other Options Are Wrong
Option A: Base the time-and-material pricing response on the original base-bid total
In procurement and contracting, Only the original base-bid total is the wrong selection for Time-and-material pricing: it tries to bypass the Time-and-material pricing checkpoint.
Option B: Base the time-and-material pricing response on a future warranty letter only
The trap in B is Only a future warranty letter. That selection is wrong because it leaves the work at an informal or incomplete stage, while Time-and-material pricing requires Agreed labor rates, material costs, equipment rates, and signed daily tickets or records; Time-and-material work is.
Option C: The contractor should use a sketch of the repair area without signed daily labor and material records
Choice C gives Only the architect's rendering. Its specific error: the option delays or omits the controlling step.
Memory Technique
Use a index tab memory cue for time-and-material pricing: the stem's condition unlocks Agreed labor rates, material costs, equipment rates, and signed daily tickets or records.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Time-and-material work documentation" to confirm that Time-and-material work is priced from agreed rates and documented labor, material, and equipment records.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass