A construction manager at risk proposes reimbursement of costs plus a fee, but the owner wants a ceiling on the total payable amount. Which contract feature addresses that ceiling?
Correct Answer
C) Guaranteed maximum price
A guaranteed maximum price establishes a contractual ceiling on the reimbursable-cost-plus-fee arrangement, subject to authorized changes. Other choices do not create the overall price ceiling.
Why This Is the Correct Answer
A guaranteed maximum price establishes a contractual ceiling on the reimbursable-cost-plus-fee arrangement, subject to authorized changes. Other choices do not create the overall price ceiling.
Why the Other Options Are Wrong
Option A: Unpriced RFI log
Choice A (Unpriced RFI log) is rejected because it leaves out the controlling GMP contract result: Guaranteed maximum price.
Option B: Voluntary alternate
In procurement and contracting, Voluntary alternate is the wrong selection for GMP contract: the choice would not get the project to Guaranteed maximum price, which is the GMP contract result verified by the source.
Option D: Use the payment application file as the backup record for gMP contract
Choice D gives Punch-list holdback only. Its specific error: it leaves the work at an informal or incomplete stage, while GMP contract requires Guaranteed maximum price. The accepted answer is Guaranteed maximum price.
Memory Technique
Link GMP contract to its book condition; a different condition means a different answer than Guaranteed maximum price.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Guaranteed maximum price contracts" to confirm that A guaranteed maximum price establishes a contractual ceiling on the reimbursable-cost-plus-fee arrangement, subject to authorized changes.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass