A public owner asks why the bid package is set up as one fixed price for a fully designed school addition. Which statement matches a lump-sum contract?
Correct Answer
A) The contractor agrees to complete defined scope for a fixed contract amount
A lump-sum contract sets a fixed price for defined contract work. Other choices describe cost-reimbursable, unit-price, or time-and-material arrangements.
Why This Is the Correct Answer
A lump-sum contract sets a fixed price for defined contract work. Other choices describe cost-reimbursable, unit-price, or time-and-material arrangements.
Why the Other Options Are Wrong
Option B: The owner pays every actual cost without a ceiling
Choice B gives The owner pays every actual cost without a ceiling. Its specific error: it leaves the work at an informal or incomplete stage, while Lump-sum contract requires The contractor agrees to complete defined scope for a fixed contract amount.
Option C: Use unit-quantity measurement as if it were a lump-sum contract
Choice C (Every pay item is measured by unit quantity only) is rejected because the option delays or omits the controlling step.
Option D: Labor is billed only by hourly tickets with no fixed scope
In procurement and contracting, Labor is billed only by hourly tickets with no fixed scope is the wrong selection for Lump-sum contract: the action skips the timing, documentation, or field-control step needed for Lump-sum contract.
Memory Technique
File lump-sum contract under a field note: condition first, number or duty second, answer The contractor agrees to complete defined scope for a fixed contract amount.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Contract types - lump sum" to confirm that A lump-sum contract sets a fixed price for defined contract work.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
