A public owner asks why the bid package is set up as one fixed price for a fully designed school addition. Which statement matches a lump-sum contract?
Correct Answer
A) Defined scope for a fixed contract amount
A lump-sum agreement prices the defined work at an agreed amount. Actual costs do not automatically replace that price; authorized changes can still alter the contract. FAR 16.202-1 illustrates the distinction from cost reimbursement for federal firm-fixed-price contracting. Unit-price measurement and hourly time-and-material billing describe different pricing arrangements. Source: https://www.acquisition.gov/far/16.202-1
Why This Is the Correct Answer
A lump-sum agreement prices the defined work at an agreed amount. Actual costs do not automatically replace that price; authorized changes can still alter the contract. FAR 16.202-1 illustrates the distinction from cost reimbursement for federal firm-fixed-price contracting. Unit-price measurement and hourly time-and-material billing describe different pricing arrangements. Source: https://www.acquisition.gov/far/16.202-1
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More NASCLA Questions
A contract permits payment for stored materials only with specified documentation. Which submission supports that payment review?
A tempered glass panel is 5 ft by 9 ft. The supplier weight is 6.5 lb per square foot. What is the panel weight before hardware?
The owner will buy major equipment directly, while the contractor remains responsible for coordination and installation. What must be clarified before the purchase is released?
Which minimum eccentric gravity load and distance does OSHA 1926.755(a)(2) specify for the column anchor-rod assembly during erection?
Using 1 refrigeration ton = 12,000 Btu/h, how many tons of cooling correspond to a scheduled capacity of 180,000 Btu/h?
On the supplied schematic practice drawing (S-741), what is the sum of the three printed chain dimensions? Use the dimension labels rather than scaling the sloping graphic.
Why are backfill lifts limited in thickness?
The specified resilient flooring and adhesive require slab moisture and pH checks before installation. Testing has not been completed, but the crew wants to meet turnover. What should happen?
The approved backfill procedure limits loose lifts to 8 inches for this soil and compactor. A crew places one 24-inch loose lift. What should be done?
Under 2021 IBC 1507.7.2, what is the minimum roof-deck slope for natural slate shingles?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Using the supplied practice drawing, using the dimensions shown for the stabilized construction entrance, what is the plan area?
Next Question
Under 29 CFR 1926.1053(b)(5)(i), what approximate setup ratio applies to an ordinary non-self-supporting portable ladder, excluding a wood job-made ladder with spliced side rails?
