In the ledger flashing section, which labeled layer is immediately above LEDGER FLASHING?

Correct Answer

C) WRB

The section stacks the layers vertically; WRB is printed immediately above LEDGER FLASHING.

Answer Options
A
LEDGER BOARD
B
RIM JOIST
C
WRB
D
SIDING

Why This Is the Correct Answer

The section stacks the layers vertically; WRB is printed immediately above LEDGER FLASHING.

Why the Other Options Are Wrong

Option A: LEDGER BOARD

LEDGER BOARD is below LEDGER FLASHING, not immediately above it.

Option B: RIM JOIST

RIM JOIST is an outside or terminal layer in the stack, not the adjacent layer asked for.

Option D: SIDING

SIDING is a different layer in the same section, but it is not the one directly above LEDGER FLASHING.

Memory Technique

In ledger flashing layer order, LEDGER FLASHING is the lower anchor; the layer above it is the only valid move.

Reference Hint

Open Sheet S-747; locate LEDGER FLASHING in the section and read the layer immediately above it.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.