Using the fall and run shown on the profile, what slope percentage is indicated?

Correct Answer

A) 2.2%

The profile shows 4 ft of fall over 180 ft of run, which is 2.2%.

Answer Options
A
2.2%
B
1.7%
C
2.8%
D
5.8%

Why This Is the Correct Answer

The profile shows 4 ft of fall over 180 ft of run, which is 2.2%.

Why the Other Options Are Wrong

Option B: 1.7%

This uses a longer run than the run dimension printed on the profile.

Option C: 2.8%

This adds 1 ft of fall that is not shown.

Option D: 5.8%

This mixes feet with percent instead of dividing fall by run.

Memory Technique

spot elevation slope check slope cue: fall is the top of the fraction, run is the bottom.

Reference Hint

Open Sheet C-874; read the profile fall and horizontal run before calculating slope.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.