From the door schedule, what fire-protection rating is scheduled for door D113?
Correct Answer
B) 45 min
On Sheet A-611, Mark D113 is the correct row; the Fire Rating cell in that row shows 45 min.
Why This Is the Correct Answer
On Sheet A-611, Mark D113 is the correct row; the Fire Rating cell in that row shows 45 min.
Why the Other Options Are Wrong
Option A: 20 min
Choice A reads the Exam 1 row D112, not the Med Gas door D113.
Option C: 90 min
Choice C reads the Stair A row D114 instead of D113.
Option D: Not rated
Choice D reads the Reception storefront row D111, not D113.
Memory Technique
Keep D113 and Fire Rating paired; any other row-column crossing is a false read.
Reference Hint
Open Sheet A-611 in the plan packet, find Mark D113, then move horizontally to the Fire Rating column.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass