During column setting, a base plate rocks because the shim pack is missing at one corner. The crane is still holding the column. What is the best field action?
Correct Answer
A) Set the column on level finished floor, pregrouted plate, leveling nuts, or adequate shims before release
OSHA 1926.755(a)(3) requires columns to be set on level finished floors, pregrouted leveling plates, leveling nuts, or shim packs adequate to transfer construction loads. Other choices release an unstable column or distort the anchorage.
Why This Is the Correct Answer
OSHA 1926.755(a)(3) requires columns to be set on level finished floors, pregrouted leveling plates, leveling nuts, or shim packs adequate to transfer construction loads. Other choices release an unstable column or distort the anchorage.
Why the Other Options Are Wrong
Option B: Release the crane and grout later, leaving column base bearing unverified
Choice B (Release the crane and grout later) is rejected because it leaves out the controlling Column base bearing result: Set the column on level finished floor, pregrouted plate, leveling nuts, or adequate shims before release.
Option C: Tighten one anchor rod to pull the plate down unevenly
In metals work, Tighten one anchor rod to pull the plate down unevenly is the wrong selection for Column base bearing: the choice would not get the project to Set the column on level finished floor, pregrouted plate, leveling nuts, or adequate shims before release, which is the Column base bearing result verified by the source.
Option D: The erection crew should cut a notch in the base plate to make it sit flat
The trap in D is Cut a notch in the base plate to make it sit flat. That selection is wrong because the option does not produce the required Column base bearing outcome, Set the column on level finished floor, pregrouted plate, leveling nuts, or adequate shims before release.
Memory Technique
Picture a stormwater map on the jobsite; column base bearing is solved by the action that leads to Set the column on level finished floor, pregrouted plate, leveling nuts, or adequate shims before release.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.755(a)(3) to confirm that OSHA 1926.755(a)(3) requires columns to be set on level finished floors, pregrouted leveling plates, leveling nuts, or shim packs adequate to transfer construction loads.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
