Thirty-six shear-tab beam connections each require four bolts. The bolt order carries an 8 percent spare allowance. What order quantity should be rounded up for the field?
Correct Answer
C) 156 bolts
Base bolts are 36 x 4 = 144. Adding 8 percent gives 144 x 1.08 = 155.52, rounded up to 156 bolts. Other choices omit the spare, round down, or use a larger arbitrary allowance.
Why This Is the Correct Answer
Base bolts are 36 x 4 = 144. Adding 8 percent gives 144 x 1.08 = 155.52, rounded up to 156 bolts. Other choices omit the spare, round down, or use a larger arbitrary allowance.
Why the Other Options Are Wrong
Option A: 144 bolts
bolt order, choice a: the answer choice lifts 144 bolts from the working line Base bolts are 36 x 4 = 144.
Option B: 150 bolts
bolt order, choice b: 150 bolts implies about 4.17 percent added to 144; the stated add-on is 8 percent in.
Option D: 160 bolts
bolt order, choice c: 160 bolts is wrong because 160 bolts implies about 11.11 percent added to 144; the stated add-on is 8 percent in.
Memory Technique
Remember bolt order as "base, adjustment, final unit"; the last unit should read 156 bolts.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Steel connection bolt quantity takeoff" to confirm that Base bolts are 36 x 4 = 144.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Electrical conduit is proposed inside a 6 in. thick structural slab before the concrete pour. Which ACI dimensional limit is the key check for conduit outside diameter in that member?
Next Question
A liquid-applied roof covering is specified on a small low-slope roof area. Which IBC minimum slope should be verified?