Open duct sections are stored on a muddy site, and the crew plans to install them without end protection or cleaning. What should be corrected?
Correct Answer
B) Protect duct openings and clean contaminated sections before installation
Duct systems should be protected from construction debris and cleaned when contaminated before installation or startup. Other choices move contamination into the system rather than preventing it.
Why This Is the Correct Answer
Duct systems should be protected from construction debris and cleaned when contaminated before installation or startup. Other choices move contamination into the system rather than preventing it.
Why the Other Options Are Wrong
Option A: The crew should install dirty duct and change filters later
The trap in A is Install dirty duct and change filters later. That selection is wrong because it leaves out the controlling Duct cleanliness result: Protect duct openings and clean contaminated sections before installation.
Option C: Spray fragrance into the duct after startup
Choice C (Spray fragrance into the duct after startup) is rejected because the option does not produce the required Duct cleanliness outcome, Protect duct openings and clean contaminated sections before installation.
Option D: The crew should leave access panels open during balancing, leaving duct cleanliness unverified
In mechanical and plumbing, Leave access panels open during balancing is the wrong selection for Duct cleanliness: it points to Leave access panels open during balancing, but.
Memory Technique
Pair duct cleanliness with the real field trigger, then choose the response that produces Protect duct openings and clean contaminated sections before installation.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use the index entry or section for "HVAC duct storage and cleanliness" to confirm that Duct systems should be protected from construction debris and cleaned when contaminated before installation or startup.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass