A video inspection of an underground sanitary run shows a belly where the pipe reverses slope for several feet. The slab has not been poured yet. What is the correct field response?
Correct Answer
C) Correct bedding and pipe grade before the run is covered
Gravity drainage depends on continuous slope; a belly should be corrected before the pipe is covered and access is lost. Other choices leave a maintainability and blockage problem.
Why This Is the Correct Answer
Gravity drainage depends on continuous slope; a belly should be corrected before the pipe is covered and access is lost. Other choices leave a maintainability and blockage problem.
Why the Other Options Are Wrong
Option A: Accept it because wastewater will eventually pass
In mechanical and plumbing, Accept it because wastewater will eventually pass is the wrong selection for Pipe slope reversal: it leaves out the controlling Pipe slope reversal result: Correct bedding and pipe grade before the run is covered.
Option B: Limit pipe slope reversal to raise the downstream cleanout only
The trap in B is Raise the downstream cleanout only. That selection is wrong because the option delays or omits the controlling step.
Option D: The MEP foreman should pour the slab and rely on future flushing
Choice D (Pour the slab and rely on future flushing) is rejected because it points to Pour the slab and rely on future flushing, but.
Memory Technique
Picture a panel space on the jobsite; pipe slope reversal is solved by the action that leads to Correct bedding and pipe grade before the run is covered.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Gravity sanitary pipe grade control" to confirm that Gravity drainage depends on continuous slope; a belly should be corrected before the pipe is covered and access is lost.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?