A video inspection of an underground sanitary run shows a belly where the pipe reverses slope for several feet. The slab has not been poured yet. What is the correct field response?

Correct Answer

C) Correct bedding and pipe grade before the run is covered

Gravity drainage depends on continuous slope; a belly should be corrected before the pipe is covered and access is lost. Other choices leave a maintainability and blockage problem.

Answer Options
A
Accept it because wastewater will eventually pass
B
Limit pipe slope reversal to raise the downstream cleanout only
C
Correct bedding and pipe grade before the run is covered
D
The MEP foreman should pour the slab and rely on future flushing

Why This Is the Correct Answer

Gravity drainage depends on continuous slope; a belly should be corrected before the pipe is covered and access is lost. Other choices leave a maintainability and blockage problem.

Why the Other Options Are Wrong

Option A: Accept it because wastewater will eventually pass

In mechanical and plumbing, Accept it because wastewater will eventually pass is the wrong selection for Pipe slope reversal: it leaves out the controlling Pipe slope reversal result: Correct bedding and pipe grade before the run is covered.

Option B: Limit pipe slope reversal to raise the downstream cleanout only

The trap in B is Raise the downstream cleanout only. That selection is wrong because the option delays or omits the controlling step.

Option D: The MEP foreman should pour the slab and rely on future flushing

Choice D (Pour the slab and rely on future flushing) is rejected because it points to Pour the slab and rely on future flushing, but.

Memory Technique

Picture a panel space on the jobsite; pipe slope reversal is solved by the action that leads to Correct bedding and pipe grade before the run is covered.

Reference Hint

Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Gravity sanitary pipe grade control" to confirm that Gravity drainage depends on continuous slope; a belly should be corrected before the pipe is covered and access is lost.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.