A CMU crew is scheduled during freezing weather, and the forecast shows temperatures dropping below freezing overnight. Which plan is appropriate for the masonry work?
Correct Answer
A) Heat materials and protect the completed work as required by the cold-weather masonry provisions
Cold-weather masonry requires temperature control of materials and protection of completed work so mortar can hydrate and bond properly. Other choices: frozen sand, antifreeze, and dry-laid joints are not acceptable quality masonry practice.
Why This Is the Correct Answer
Cold-weather masonry requires temperature control of materials and protection of completed work so mortar can hydrate and bond properly.
Why the Other Options Are Wrong
Option B: Use frozen sand because it will thaw in the mortar, leaving cold weather masonry unverified
Choice B (Use frozen sand because it will thaw in the mortar) is rejected because the option does not produce the required Cold weather masonry outcome, Heat materials and protect the completed work as required by the cold-weather masonry provisions.
Option C: Add automotive antifreeze to the mortar
In masonry work, Add automotive antifreeze to the mortar is the wrong selection for Cold weather masonry: it points to Add automotive antifreeze to the mortar, but.
Option D: Lay units dry and point the joints in spring
The trap in D is Lay units dry and point the joints in spring. That selection is wrong because it answers the Cold weather masonry prompt with the wrong practical move.
Memory Technique
Use the phrase "problem, control, result" for cold weather masonry; the result side is Heat materials and protect the completed work as required by the cold-weather masonry provisions.
Reference Hint
Open Modern Masonry - Brick, Block, Stone, 9th Ed., 2020; use the index entry or section for "Cold weather masonry construction" to confirm that Cold-weather masonry requires temperature control of materials and protection of completed work so mortar can hydrate and bond properly.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
