There are 45 open inspection punch items and the team can clear 15 per day. How many days are required?

Correct Answer

B) 3 days

Backlog duration is 45 / 15 = 3 days.

Answer Options
A
2 days
B
3 days
C
5 days
D
675 days

Why This Is the Correct Answer

Backlog duration is 45 / 15 = 3 days.

Why the Other Options Are Wrong

Option A: 2 days

inspection backlog days, choice a: 2 days backs into 0.67 when divided by 45 / 15; the accepted setup gives 1 on that same base.

Option C: 5 days

inspection backlog days, choice b: 5 days backs into 0.33 when divided by 15; the accepted setup gives 0.2 on that same base.

Option D: 675 days

inspection backlog days, choice d: 45 x 15 gives 675 days. That calculation follows multiplies those two listed numbers.

Memory Technique

Keep a fastener row beside inspection backlog days: if one number is skipped, the option drifts away from 3 days.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Backlog duration is 45 / 15 = 3 days.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.