A reviewer can close 7 items per day and has 28 open submittal comments. How many days are needed?

Correct Answer

C) 4 days

Backlog duration is 28 / 7 = 4 days.

Answer Options
A
3 days
B
5 days
C
4 days
D
196 days

Why This Is the Correct Answer

Backlog duration is 28 / 7 = 4 days.

Why the Other Options Are Wrong

Option A: 3 days

document review backlog, choice a: 3 days backs into 0.43 when divided by 7; the accepted setup gives 0.57 on that same base.

Option B: 5 days

document review backlog, choice c: 5 days backs into 0.71 when divided by 7; the accepted setup gives 0.57 on that same base.

Option D: 196 days

document review backlog, choice d: the number 196 days comes from 7 x 28.

Memory Technique

Store document review backlog with its last math move; nearby answers are usually unfinished versions of 4 days.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Backlog duration is 28 / 7 = 4 days.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.