On a fast-track school project, what construction stair handrail height range is checked?
Correct Answer
A) 30 in. to 37 in.
30 in. to 37 in. is the controlling requirement.1052(c)(6). Other choices: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 220.
Why This Is the Correct Answer
30 in. to 37 in. is the controlling requirement.1052(c)(6).
Why the Other Options Are Wrong
Option B: 24 in. to 30 in.
The trap in B is 24 in. to 30 in.; without satisfying the required project control. That selection is wrong because 24 in. to 30 in.; without satisfying the required project control is a different published number than the cited Handrail height value; 29 CFR 1926.1052(c)(6) supports 30 in.
Option C: 38 in. to 45 in.
Choice C gives 38 in. to 45 in. Its specific error: 38 in. to 45 in. is a different published number than the cited Handrail height value; 29 CFR 1926.1052(c)(6) supports 30 in. to 37 in. The accepted answer is 30 in. to 37 in.
Option D: 42 in. plus or minus 3 in.
Choice D (42 in. plus or minus 3 in.) is rejected because 42 in. plus or minus 3 in. is a different published number than the cited Handrail height value; 29 CFR 1926.1052(c)(6) supports 30 in. to 37 in. The cited answer is 30 in. to 37 in.
Memory Technique
Use a checkpoint memory cue for handrail height: the stem's condition unlocks 30 in. to 37 in.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.1052(c)(6) to confirm that 30 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
