The owner cannot train maintenance staff because O&M data is missing. What closeout control would have reduced the problem?
Correct Answer
C) Track O&M submittals by specification section and required turnover date.
O&M requirements should be tracked before turnover so training and operation can proceed.
Why This Is the Correct Answer
O&M requirements should be tracked before turnover so training and operation can proceed.
Why the Other Options Are Wrong
Option A: The owner should wait for final payment to request all manuals
Choice A (Wait for final payment to request all manuals.) is rejected because the option delays or omits the controlling step.
Option B: The owner should use the bid bond as an O&M manual
In general project requirements, Use the bid bond as an O&M manual. is the wrong selection for Closeout O&M chase: it names a financial document or payment mechanism, not the Closeout O&M chase action/result stated by Track O&M submittals by specification section and required turnover date.
Option D: Document the condition in the daily report and wait for the next closeout O&M chase review
Choice D gives Delete owner training. Its specific error: it removes the controlling Closeout O&M chase requirement instead of meeting it.
Memory Technique
Pair closeout O&M chase with the real field trigger, then choose the response that produces Track O&M submittals by specification section and required turnover date.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that O&M requirements should be tracked before turnover so training and operation can proceed.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass