EstatePass
NASCLAGeneral Reqmedium22% of exam part

After the revised drawing is issued, how far from the excavation edge should spoil be kept unless retained?

Correct Answer

A) At least 2 ft

At least 2 ft is the controlling requirement.651(j)(2). Other choices: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 85.

Answer Options
A
At least 2 ft
B
6 in. from the excavation edge
C
12 in. from the excavation edge
D
4 ft from the excavation edge

Why This Is the Correct Answer

At least 2 ft is the controlling requirement.651(j)(2).

Why the Other Options Are Wrong

Option B: 6 in. from the excavation edge

Choice B gives 6 in. Its specific error: 6 in. is a different published number than the cited Spoil setback value; 29 CFR 1926.651(j)(2) supports At least 2 ft. The accepted answer is At least 2 ft.

Option C: 12 in. from the excavation edge

Choice C (12 in.) is rejected because 12 in. is a different published number than the cited Spoil setback value; 29 CFR 1926.651(j)(2) supports At least 2 ft. The cited answer is At least 2 ft.

Option D: 4 ft from the excavation edge

In general project requirements, 4 ft is the wrong selection for Spoil setback: 4 ft is a different published number than the cited Spoil setback value; 29 CFR 1926.651(j)(2) supports At least 2 ft.

Memory Technique

Use a anchor memory cue for spoil setback: the stem's condition unlocks At least 2 ft.

Reference Hint

Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.651(j)(2) to confirm that At least 2 ft is the controlling requirement.651(j)(2).

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.