Why are shop drawings and product data submitted before related work is fabricated or installed?
Correct Answer
B) To show how proposed items comply with the contract documents for review
Submittals communicate the contractor's proposed products and details for review against contract requirements before work proceeds. Other choices overstate or misunderstand the review function.
Why This Is the Correct Answer
Submittals communicate the contractor's proposed products and details for review against contract requirements before work proceeds. Other choices overstate or misunderstand the review function.
Why the Other Options Are Wrong
Option A: Document the condition in the daily report and wait for the next submittal purpose review
The trap in A is To replace field supervision. That selection is wrong because it treats Submittal purpose as optional.
Option C: Treat the item as a closeout correction tied to submittal purpose
Choice C (To transfer design responsibility for every detail to the owner) is rejected because it leaves out the controlling Submittal purpose result: To show how proposed items comply with the contract documents for review.
Option D: Proceed with the work and treat the submittal as informational only
In general project requirements, To eliminate the need for inspections is the wrong selection for Submittal purpose: it treats Submittal purpose as optional.
Memory Technique
Picture submittal purpose doing the job; the answer names that job as To show how proposed items comply with the contract documents for review.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Submittal administration" to confirm that Submittals communicate the contractor's proposed products and details for review against contract requirements before work proceeds.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass