What does the critical path represent in a construction schedule?
Correct Answer
C) The longest path of dependent activities controlling project duration
The critical path is the longest chain of dependent activities that determines the project completion date. Other choices confuse it with cost ranking, simple work, or isolated inspections.
Why This Is the Correct Answer
The critical path is the longest chain of dependent activities that determines the project completion date. Other choices confuse it with cost ranking, simple work, or isolated inspections.
Why the Other Options Are Wrong
Option A: The shortest sequence of easy tasks
In general project requirements, The shortest sequence of easy tasks is the wrong selection for Critical path: the choice would not get the project to The longest path of dependent activities controlling project duration, which is the Critical path result verified by the source.
Option B: Base the critical path response on activities with the lowest cost only
The trap in B is Only activities with the lowest cost. That selection is wrong because it leaves the work at an informal or incomplete stage, while Critical path requires The longest path of dependent activities controlling project duration; The critical path is the longest dependent path controlling project duration.
Option D: Classify the condition as a list of inspections unrelated to completion
Choice D (A list of inspections unrelated to completion) is rejected because it answers the Critical path prompt with the wrong practical move.
Memory Technique
Keep critical path as a cause-to-effect card with The longest path of dependent activities controlling project duration on the back.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Critical-path method scheduling" to confirm that The critical path is the longest chain of dependent activities that determines the project completion date.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
