In day-to-day construction management, what is quality control primarily concerned with?
Correct Answer
A) Checking and controlling the work so it conforms to the contract requirements
Quality control is the contractor's active process for checking, controlling, and correcting work so it meets contract requirements. Other choices bypass the documents or postpone defects.
Why This Is the Correct Answer
Quality control is the contractor's active process for checking, controlling, and correcting work so it meets contract requirements. Other choices bypass the documents or postpone defects.
Why the Other Options Are Wrong
Option B: Replacing the contract documents after award
In general project requirements, Replacing the contract documents after award is the wrong selection for Quality control: it leaves out the controlling Quality control result: Checking and controlling the work so it conforms to the contract requirements.
Option C: Avoiding all inspections to save time, leaving quality control unverified
The trap in C is Avoiding all inspections to save time. That selection is wrong because the choice would not get the project to Checking and controlling the work so it conforms to the contract requirements, which is the Quality control result verified by the source; Quality control checks and controls work to meet contract requirements.
Option D: Limit quality control to shifting every deficiency to final payment only
Choice D gives Shifting every deficiency to final payment only. Its specific error: it tries to bypass the Quality control checkpoint.
Memory Technique
Make quality control a purpose cue; if the choice changes the purpose, it cannot be Checking and controlling the work so it conforms to the contract requirements.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Quality-control management" to confirm that Quality control is the contractor's active process for checking, controlling, and correcting work so it meets contract requirements.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass