A wall finish mockup is rejected for texture and corner detail, but the crew wants to start the remaining floors to save time. What should happen?
Correct Answer
B) Correct and obtain acceptance of the mockup before production work proceeds
Mockups set the accepted quality standard before repeated work begins. Other choices multiply a known defect or erase the purpose of the mockup.
Why This Is the Correct Answer
Mockups set the accepted quality standard before repeated work begins. Other choices multiply a known defect or erase the purpose of the mockup.
Why the Other Options Are Wrong
Option A: Proceed because the mockup is not part of the final work
Choice A (Proceed because the mockup is not part of the final work) is rejected because it answers the Mockup acceptance prompt with the wrong practical move.
Option C: The crew should install the finish and negotiate acceptance later
The trap in C is Install the finish and negotiate acceptance later. That selection is wrong because the choice would not get the project to Correct and obtain acceptance of the mockup before production work proceeds, which is the Mockup acceptance result verified by the source; Rejected mockups should be corrected and accepted before production work proceeds.
Option D: The crew should use a different texture on each floor
Choice D gives Use a different texture on each floor. Its specific error: the option does not produce the required Mockup acceptance outcome, Correct and obtain acceptance of the mockup before production work proceeds.
Memory Technique
Pair mockup acceptance with the real field trigger, then choose the response that produces Correct and obtain acceptance of the mockup before production work proceeds.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Mockups and quality standards" to confirm that Mockups set the accepted quality standard before repeated work begins.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass