A guardrail section is removed to land materials on an upper floor, and workers continue walking near the open edge after the load is placed. What is the proper response?

Correct Answer

C) Restore the guardrail or provide another compliant fall-protection method before workers remain exposed

When a guardrail is removed, exposure at the edge must be controlled by replacing protection or using another compliant method. Other choices substitute awareness or markings for fall protection.

Answer Options
A
Leave the opening because the lift is finished
B
Limit guardrail interruption to mark the opening with paint
C
Restore the guardrail or provide another compliant fall-protection method before workers remain exposed
D
Ask workers to stay alert until the end of shift

Why This Is the Correct Answer

When a guardrail is removed, exposure at the edge must be controlled by replacing protection or using another compliant method. Other choices substitute awareness or markings for fall protection.

Why the Other Options Are Wrong

Option A: Leave the opening because the lift is finished

The trap in A is Leave the opening because the lift is finished. That selection is wrong because the option does not produce the required Guardrail interruption outcome, Restore the guardrail or provide another compliant fall-protection method before workers remain exposed.

Option B: Limit guardrail interruption to mark the opening with paint

Choice B gives Mark the opening with paint only. Its specific error: it leaves the work at an informal or incomplete stage, while Guardrail interruption requires Restore the guardrail or provide another compliant fall-protection method before workers remain.

Option D: Ask workers to stay alert until the end of shift

In general project requirements, Ask workers to stay alert until the end of shift is the wrong selection for Guardrail interruption: it leaves out the controlling Guardrail interruption result: Restore the guardrail or provide another compliant fall-protection method before workers remain exposed.

Memory Technique

Tag the scene with guardrail interruption: wrong actor or wrong timing means the fix is not Restore the guardrail or provide another compliant fall-protection method before workers remain exposed.

Reference Hint

Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.501 and 1926.502 to confirm that When a guardrail is removed, exposure at the edge must be controlled by replacing protection or using another compliant method.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.