Heavy rain falls overnight into an open trench. The crew arrives before the planned morning utility work. What should occur before workers enter?

Correct Answer

D) Have the competent person reinspect and correct hazards before entry

Excavations require competent-person inspection after events such as rainstorms that can increase hazard. Other choices rely on stale conditions or put employees into a changed excavation before inspection.

Answer Options
A
Enter if the trench looked safe yesterday
B
Pump water only after employees enter
C
The crew should use the previous week's soil classification without review
D
Have the competent person reinspect and correct hazards before entry

Why This Is the Correct Answer

Excavations require competent-person inspection after events such as rainstorms that can increase hazard. Other choices rely on stale conditions or put employees into a changed excavation before inspection.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.