Heavy rain falls overnight into an open trench. The crew arrives before the planned morning utility work. What should occur before workers enter?
Correct Answer
D) Have the competent person reinspect and correct hazards before entry
Excavations require competent-person inspection after events such as rainstorms that can increase hazard. Other choices rely on stale conditions or put employees into a changed excavation before inspection.
Why This Is the Correct Answer
Excavations require competent-person inspection after events such as rainstorms that can increase hazard. Other choices rely on stale conditions or put employees into a changed excavation before inspection.
Why the Other Options Are Wrong
Option A: Enter if the trench looked safe yesterday
In general project requirements, Enter if the trench looked safe yesterday is the wrong selection for Competent-person inspection: the option does not produce the required Competent-person inspection outcome, Have the competent person reinspect and correct hazards before entry.
Option B: Pump water only after employees enter
The trap in B is Pump water only after employees enter. That selection is wrong because it leaves the work at an informal or incomplete stage, while Competent-person inspection requires Have the competent person reinspect and correct hazards before entry; A competent person inspects excavations after hazard-increasing occurrences such as rainstorms.
Option C: The crew should use the previous week's soil classification without review
Choice C gives Use the previous week's soil classification without review. Its specific error: the option delays or omits the controlling step.
Memory Technique
Remember competent-person inspection by its jobsite consequence: the correct move points to Have the competent person reinspect and correct hazards before entry.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.651(k)(1) to confirm that Excavations require competent-person inspection after events such as rainstorms that can increase hazard.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass