A wall assembly is ready for cover, but the required in-wall inspection has not occurred. What is the correct quality-control response?
Correct Answer
C) Hold cover work until the required inspection is completed
A required hold-point inspection must occur before the work is concealed. Other choices remove the inspector's ability to verify the hidden condition and invite destructive reinspection.
Why This Is the Correct Answer
A required hold-point inspection must occur before the work is concealed. Other choices remove the inspector's ability to verify the hidden condition and invite destructive reinspection.
Why the Other Options Are Wrong
Option A: Cover the wall and photograph the outside face
Choice A gives Cover the wall and photograph the outside face. Its specific error: the choice would not get the project to Hold cover work until the required inspection is completed, which is the Inspection hold point result verified by the source.
Option B: Ask the inspector to sign off after drywall finishing
Choice B (Ask the inspector to sign off after drywall finishing) is rejected because the option does not produce the required Inspection hold point outcome, Hold cover work until the required inspection is completed.
Option D: Cover only the areas that are hard to access later
The trap in D is Cover only the areas that are hard to access later. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Inspection hold point.
Memory Technique
Pair inspection hold point with the real field trigger, then choose the response that produces Hold cover work until the required inspection is completed.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Inspection hold points" to confirm that A required hold-point inspection must occur before the work is concealed.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
