Ceiling tile arrives before the finish submittal is reviewed, and the foreman wants to install it to protect the schedule. What should the superintendent do?
Correct Answer
B) Hold installation until the submittal is reviewed and discrepancies are resolved
Submittals are used to confirm proposed products and details before related work is installed. Other choices create rework risk or bypass the required review process.
Why This Is the Correct Answer
Submittals are used to confirm proposed products and details before related work is installed. Other choices create rework risk or bypass the required review process.
Why the Other Options Are Wrong
Option A: The superintendent should install it and ask for approval afterward
The trap in A is Install it and ask for approval afterward. That selection is wrong because the option does not produce the required Submittal control outcome, Hold installation until the submittal is reviewed and discrepancies are resolved.
Option C: The superintendent should install only rooms not visible to the owner
Choice C (Install only rooms not visible to the owner) is rejected because the option delays or omits the controlling step.
Option D: Change the specification to match the delivered tile
In general project requirements, Change the specification to match the delivered tile is the wrong selection for Submittal control: it leaves out the controlling Submittal control result: Hold installation until the submittal is reviewed and discrepancies are resolved.
Memory Technique
Picture a anchor on the jobsite; submittal control is solved by the action that leads to Hold installation until the submittal is reviewed and discrepancies are resolved.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Submittal and quality-control procedures" to confirm that Submittals are used to confirm proposed products and details before related work is installed.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
