Ceiling tile arrives before the finish submittal is reviewed, and the foreman wants to install it to protect the schedule. What should the superintendent do?

Correct Answer

B) Hold installation until the submittal is reviewed and discrepancies are resolved

Submittals are used to confirm proposed products and details before related work is installed. Other choices create rework risk or bypass the required review process.

Answer Options
A
The superintendent should install it and ask for approval afterward
B
Hold installation until the submittal is reviewed and discrepancies are resolved
C
The superintendent should install only rooms not visible to the owner
D
Change the specification to match the delivered tile

Why This Is the Correct Answer

Submittals are used to confirm proposed products and details before related work is installed. Other choices create rework risk or bypass the required review process.

Why the Other Options Are Wrong

Option A: The superintendent should install it and ask for approval afterward

The trap in A is Install it and ask for approval afterward. That selection is wrong because the option does not produce the required Submittal control outcome, Hold installation until the submittal is reviewed and discrepancies are resolved.

Option C: The superintendent should install only rooms not visible to the owner

Choice C (Install only rooms not visible to the owner) is rejected because the option delays or omits the controlling step.

Option D: Change the specification to match the delivered tile

In general project requirements, Change the specification to match the delivered tile is the wrong selection for Submittal control: it leaves out the controlling Submittal control result: Hold installation until the submittal is reviewed and discrepancies are resolved.

Memory Technique

Picture a anchor on the jobsite; submittal control is solved by the action that leads to Hold installation until the submittal is reviewed and discrepancies are resolved.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Submittal and quality-control procedures" to confirm that Submittals are used to confirm proposed products and details before related work is installed.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.