A temporary weather-protection scope is estimated at 320 labor-hours and must finish in 5 eight-hour workdays. How many workers are needed?

Correct Answer

A) 8 workers

Available hours per worker are 5 x 8 = 40. Required workers are 320 / 40 = 8. Other choices use too few hours, round without calculation, or add extra crew not supported by the estimate.

Answer Options
A
8 workers
B
6 workers
C
10 workers
D
12 workers

Why This Is the Correct Answer

Available hours per worker are 5 x 8 = 40. Required workers are 320 / 40 = 8. Other choices use too few hours, round without calculation, or add extra crew not supported by the estimate.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.