A temporary stairway has four risers and an open side. Which trigger requires handrail and stairrail protection?

Correct Answer

D) Four or more risers or rising more than 30 in., whichever is less

Stairways with four or more risers or rising more than 30 in., whichever is less, must have the required handrail and stairrail protection. Other choices add thresholds that are not the OSHA construction trigger.

Answer Options
A
Base the temporary stair handrails response on stairs with ten or more risers
B
Base the temporary stair handrails response on stairs serving the public only
C
Limit temporary stair handrails to stairs wider than 44 in.
D
Four or more risers or rising more than 30 in., whichever is less

Why This Is the Correct Answer

Stairways with four or more risers or rising more than 30 in., whichever is less, must have the required handrail and stairrail protection. Other choices add thresholds that are not the OSHA construction trigger.

Why the Other Options Are Wrong

Option A: Base the temporary stair handrails response on stairs with ten or more risers

Choice A (Only stairs with ten or more risers) is rejected because it leaves the work at an informal or incomplete stage, while Temporary stair handrails requires F.

Option B: Base the temporary stair handrails response on stairs serving the public only

In general project requirements, Only stairs serving the public is the wrong selection for Temporary stair handrails: the option delays or omits the controlling step.

Option C: Limit temporary stair handrails to stairs wider than 44 in.

The trap in C is Only stairs wider than 44 in. That selection is wrong because Only stairs wider than 44 in. is a different published number than the cited Temporary stair handrails value; 29 CFR 1926.1052(c)(1) supports F.

Memory Technique

Make temporary stair handrails a tabbed card: cite the exact condition, then choose Four or more risers or rising more than 30 in., whichever is less.

Reference Hint

Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.1052(c)(1) to confirm that Stairways with four or more risers or rising more than 30 in., whichever is less, must have the required handrail and stairrail protection.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.