Workers need to move between two work levels where no ramp, runway, embankment, or personnel hoist is provided. At what break in elevation must a stairway or ladder be provided?
Correct Answer
B) 19 in.
A stairway or ladder is required at personnel access points where there is a break in elevation of 19 in. or more and no alternate access method is provided. Other choices are too low or confuse the rule with handrail thresholds.
Why This Is the Correct Answer
A stairway or ladder is required at personnel access points where there is a break in elevation of 19 in. or more and no alternate access method is provided. Other choices are too low or confuse the rule with handrail thresholds.
Why the Other Options Are Wrong
Option A: 12 in.
Choice A gives 12 in. Its specific error: 12 in. is not the OSHA ladder setup, extension, or access dimension cited here.
Option C: 30 in.
In general project requirements, 30 in. is the wrong selection for Stairway or ladder access: 30 in. is not the OSHA ladder setup, extension, or access dimension cited here.
Option D: 48 in.
The trap in D is 48 in. That selection is wrong because 48 in. is not the OSHA ladder setup, extension, or access dimension cited here.
Memory Technique
File stairway or ladder access under a stormwater map: condition first, number or duty second, answer 19 in.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.1051(a) to confirm that A stairway or ladder is required at personnel access points where there is a break in elevation of 19 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
