A supported scaffold is being reviewed before masonry crews load plank with workers and materials. What capacity factor applies to the scaffold and its components?
Correct Answer
D) Four times the maximum intended load
Each scaffold and scaffold component must support its own weight and at least four times the maximum intended load applied or transmitted to it. Other choices are below the OSHA scaffold capacity requirement.
Why This Is the Correct Answer
Each scaffold and scaffold component must support its own weight and at least four times the maximum intended load applied or transmitted to it. Other choices are below the OSHA scaffold capacity requirement.
Why the Other Options Are Wrong
Option A: Select equal to the intended load for scaffold capacity
Choice A gives Equal to the intended load. Its specific error: it leaves out the controlling Scaffold capacity result: Four times the maximum intended load.
Option B: Apply the Two times the intended load limit to the scaffold capacity check
Choice B (Two times the intended load) is rejected because the choice would not get the project to Four times the maximum intended load, which is the Scaffold capacity result verified by the source. The cited answer is Four times the maximum intended load.
Option C: Treat Three times the intended load as the controlling scaffold capacity result
In general project requirements, Three times the intended load is the wrong selection for Scaffold capacity: the option does not produce the required Scaffold capacity outcome, Four times the maximum intended load.
Memory Technique
Make scaffold capacity a tabbed card: cite the exact condition, then choose Four times the maximum intended load.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.451(a)(1) to confirm that Each scaffold and scaffold component must support its own weight and at least four times the maximum intended load applied or transmitted to it.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?