A long gypsum board corridor ceiling has no relief in a continuous plane. What maximum control-joint spacing is commonly used for large gypsum board expanses?
Correct Answer
C) 30 ft
Gypsum board control-joint guidance commonly limits large continuous expanses to about 30 ft between control joints unless the design documents require closer spacing. Other choices are either overly tight or too wide.
Why This Is the Correct Answer
Gypsum board control-joint guidance commonly limits large continuous expanses to about 30 ft between control joints unless the design documents require closer spacing. Other choices are either overly tight or too wide.
Why the Other Options Are Wrong
Option A: 10 ft
The trap in A is 10 ft. That selection is wrong because 10 ft is a different published number than the cited Gypsum board control joints value; Gypsum board control joint spacing supports 30 ft; Gypsum board control joints are commonly spaced not more than 30 ft in large expanses.
Option B: 20 ft
Choice B gives 20 ft. Its specific error: 20 ft is a different published number than the cited Gypsum board control joints value; Gypsum board control joint spacing supports 30 ft. The accepted answer is 30 ft.
Option D: 60 ft
In finishes, 60 ft is the wrong selection for Gypsum board control joints: 60 ft is a different published number than the cited Gypsum board control joints value; Gypsum board control joint spacing supports 30 ft.
Memory Technique
File gypsum board control joints under a field note: condition first, number or duty second, answer 30 ft.
Reference Hint
Open Gypsum Construction Handbook, 7th Ed., 2014; use the index entry or section for "Gypsum board control joint spacing" to confirm that Gypsum board control-joint guidance commonly limits large continuous expanses to about 30 ft between control joints unless the design documents require closer spacing.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
