A 30 ft by 24 ft slab has one layer of No. 4 bars at 12 in. on center each way, with bars placed at both edges. What total bar length is required before laps and waste?
Correct Answer
A) 1,494 lf
Bars running 30 ft are spaced across 24 ft: 24/1 + 1 = 25 bars, so 25 x 30 = 750 lf. Bars running 24 ft are spaced across 30 ft: 30/1 + 1 = 31 bars, so 31 x 24 = 744 lf. Total is 1,494 lf. Other choices: 1,440 lf misses the edge-bar count, 1,248 lf omits one direction count, and 1,548 lf adds a lap allowance not stated.
Why This Is the Correct Answer
Bars running 30 ft are spaced across 24 ft: 24/1 + 1 = 25 bars, so 25 x 30 = 750 lf. Bars running 24 ft are spaced across 30 ft: 30/1 + 1 = 31 bars, so 31 x 24 = 744 lf. Total is 1,494 lf.
Why the Other Options Are Wrong
Option B: 1,440 lf
reinforcing quantity, choice b: 30 x 4 x 12 gives 1,440 lf. That calculation follows multiplies three stated factors.
Option C: 1,248 lf
reinforcing quantity, choice c: 1,248 lf backs into 1,248 when divided by 1; the accepted setup gives 1,494 on that same base.
Option D: 1,548 lf
reinforcing quantity, choice d: 1,548 lf backs into 1,548 when divided by 1; the accepted setup gives 1,494 on that same base.
Memory Technique
Remember reinforcing quantity as "base, adjustment, final unit"; the last unit should read 1,494 lf.
Reference Hint
Open Placing Reinforcing Bars, CRSI, 10th Ed., 2019; use the index entry or section for "Reinforcing bar quantity takeoff - grid spacing" to confirm that Bars running 30 ft are spaced across 24 ft: 24/1 + 1 = 25 bars, so 25 x 30 = 750 lf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
