The Palm Coast project has this stairway condition: temporary stairs lack handrail protection. Which safety control applies?

Correct Answer

D) install stair rail system

Stairways and access routes must be kept protected and clear for employee use.

Answer Options
A
use the wall side
B
a rope handline
C
a hold-the-rail sign
D
install stair rail system

Why This Is the Correct Answer

Stairways and access routes must be kept protected and clear for employee use.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.