EstatePass
Project MgmtSafetymedium20% of exam part

The Gainesville project has this chemical communication issue: crew has not been briefed before using solvent. Which safety control should be completed?

Correct Answer

C) hazard communication briefing

Hazard communication controls include labels, SDS access, and worker instruction for chemical hazards.

Answer Options
A
post the SDS, assume they read
B
brief the lead to relay it
C
hazard communication briefing
D
hand a sheet, no explaining

Why This Is the Correct Answer

Hazard communication controls include labels, SDS access, and worker instruction for chemical hazards.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.