A Jacksonville lift plan has this rigging issue: sling tag is unreadable. Which safety action applies before the pick?
Correct Answer
D) rigging inspection hold
Rigging must be inspected, load weights confirmed, and damaged gear removed before lifting.
Why This Is the Correct Answer
Rigging must be inspected, load weights confirmed, and damaged gear removed before lifting.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the area summary schedule, what occupancy is listed for Zone D?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The Tampa crew finds this floor-opening condition: cover shifted after material staging. Which safety action is required before traffic continues?
Next Question
While preparing the field-takeoff reconciliation for the library reading-room addition, the deck area for the temporary dry-in totals 7720 SF. With 10% waste, how many roofing squares are needed?
