The Deerfield Beach project has this chemical communication issue: chemical container has no jobsite label. Which safety control should be completed?

Correct Answer

D) hazard label correction

Hazard communication controls include labels, SDS access, and worker instruction for chemical hazards.

Answer Options
A
store it away from the crew
B
workers smell to identify it
C
only the opener may use it
D
hazard label correction

Why This Is the Correct Answer

Hazard communication controls include labels, SDS access, and worker instruction for chemical hazards.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.