A Palm Bay task creates flying-particle exposure because a crew is chipping concrete overhead. Which PPE control is required?
Correct Answer
C) impact protection enforcement
Eye and face protection must match cutting, grinding, chipping, and similar exposure.
Why This Is the Correct Answer
Eye and face protection must match cutting, grinding, chipping, and similar exposure.
Why the Other Options Are Wrong
Option A: a bump cap, not a hard hat
a bump cap, not a hard hat puts the item in the wrong financial bucket, timing, base, or comparison for eye and face protection.
Option B: earplugs for the noise
earplugs for the noise puts the item in the wrong financial bucket, timing, base, or comparison for eye and face protection.
Option D: knee pads
knee pads puts the item in the wrong financial bucket, timing, base, or comparison for eye and face protection.
Memory Technique
Eye And Face ledger for Safety Manager: put match in the right drawer.
Reference Hint
Open-book path: tab OSHA 29 CFR 1926 to Subpart E, 1926.102 Eye and face protection; verify the OSHA safety threshold or jobsite control before answering.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass