While preparing the field-takeoff reconciliation for the seafood-market cooler room, the utility-room wall area for FRP wall panels is 7920 SF. With 5% waste and 32 SF per sheet or panel, how many panels are required?
Correct Answer
C) 260 panels
Sheet count equals area with waste divided by coverage per sheet or panel, rounded up.
Why This Is the Correct Answer
Sheet count equals area with waste divided by coverage per sheet or panel, rounded up.
Why the Other Options Are Wrong
Option A: 248 panels
248 panels is below the supported result for frp wall panels; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 130 panels
130 panels is below the supported result for frp wall panels; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 264 panels
264 panels is above the supported result for frp wall panels; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Measure to sheet, adjust for count, then let Carpenter Checks set the finish line.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Special wall panels; sheet coverage; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?