While preparing the field-takeoff reconciliation for the clubhouse cart-storage bay, the patching mortar requires 40.1 CY of spall repair volume. If each bag yields 0.38 CY, how many bags are needed?
Correct Answer
C) 106 bags
Bag count equals required volume divided by bag yield, rounded up.
Why This Is the Correct Answer
Bag count equals required volume divided by bag yield, rounded up.
Why the Other Options Are Wrong
Option A: 15 bags
15 bags is below the supported result for patching mortar; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 108 bags
108 bags is above the supported result for patching mortar; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 107 bags
107 bags is above the supported result for patching mortar; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Patching Mortar cart for Foreman Checks: bag first, count second, whole units last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete repair; patch material yield; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass