While preparing the material-order review for the grocery receiving dock, the cover-plate order includes 216 LF at $58 each before a 12% contractor markup. What extended price should be carried?
Correct Answer
B) $14,031
Extended price equals quantity times unit price, then multiplied by the markup factor.
Why This Is the Correct Answer
Extended price equals quantity times unit price, then multiplied by the markup factor.
Why the Other Options Are Wrong
Option A: $12,528
$12,528 is below the supported result for expansion-joint covers cost extension; it likely uses the wrong base, period, or account bucket.
Option C: $14,658
$14,658 is above the supported result for expansion-joint covers cost extension; it likely adds an unsupported amount or compares the wrong financial base.
Option D: $12,540
$12,540 is below the supported result for expansion-joint covers cost extension; it likely uses the wrong base, period, or account bucket.
Memory Technique
Expansion-Joint Covers fence: markup starts at cost, margin looks back from price.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Joint protection; linear material pricing; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass