While preparing the material-order review for the bank drive-through canopy, a site crew must complete 17050 LF of concrete sidewalk placement. If planned production is 400 LF per day, how many whole work days should be scheduled?
Correct Answer
B) 43 work days
Crew days equal quantity divided by daily production, rounded up to whole days.
Why This Is the Correct Answer
Crew days equal quantity divided by daily production, rounded up to whole days.
Why the Other Options Are Wrong
Option A: 36 work days
36 work days is below the supported result for concrete sidewalk placement productivity; it likely uses the wrong base, period, or account bucket.
Option C: 45 work days
45 work days is above the supported result for concrete sidewalk placement productivity; it likely adds an unsupported amount or compares the wrong financial base.
Option D: 44 work days
44 work days is above the supported result for concrete sidewalk placement productivity; it likely adds an unsupported amount or compares the wrong financial base.
Memory Technique
Concrete Sidewalk drawer for Superintendent Schedules: label crew before counting dollars.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Site concrete; crew production planning; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass