While preparing the preconstruction estimate lock for the retail vestibule replacement, the parapet run requires 534 LF of aluminum counterflashing plus 6% waste. Stock comes in 10 ft pieces. How many pieces are required?
Correct Answer
A) 57 pieces
Linear stock count equals required length with waste divided by stock length, rounded up.
Why This Is the Correct Answer
Linear stock count equals required length with waste divided by stock length, rounded up.
Why the Other Options Are Wrong
Option B: 53 pieces
53 pieces is below the supported result for aluminum counterflashing; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 60 pieces
60 pieces is above the supported result for aluminum counterflashing; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 56 pieces
56 pieces is below the supported result for aluminum counterflashing; it likely omits allowance, conversion, coverage, or final round-up.
Memory Technique
Measure to linear, adjust for stock, then let Field Engineer set the finish line.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Flashing and sheet metal; stock-length takeoff; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass