While preparing the buyout verification pass for the civic-center ticket lobby, a reinforced slab panel is 57 ft by 18 ft by 5 in. Including 3% waste, how many cubic yards of concrete are needed?

Correct Answer

D) 16.3 CY

Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.

Answer Options
A
15.8 CY
B
190.0 CY
C
18.3 CY
D
16.3 CY

Why This Is the Correct Answer

Convert slab thickness from inches to feet, divide by 27 cubic feet per cubic yard, then add waste.

Why the Other Options Are Wrong

Option A: 15.8 CY

15.8 CY is below the supported result for equipment housekeeping slab; it likely omits allowance, conversion, coverage, or final round-up.

Option B: 190.0 CY

190.0 CY is above the supported result for equipment housekeeping slab; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option C: 18.3 CY

18.3 CY is above the supported result for equipment housekeeping slab; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Superintendent Validates takeoff: count the condition before counting the package.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Concrete methods; slab volume estimating; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.