During the next-week procurement cycle at the plant-nursery sales canopy, the stored-material billing shows a $176,000 approved stored material. If 5% is withheld, what retainage amount should be shown?
Correct Answer
C) $8,800
Retainage equals the approved amount multiplied by the retainage percentage.
Why This Is the Correct Answer
Retainage equals the approved amount multiplied by the retainage percentage.
Why the Other Options Are Wrong
Option A: $13,200
$13,200 is above the supported result for stored-material billing; it likely adds an unsupported amount or compares the wrong financial base.
Option B: $167,200
$167,200 is above the supported result for stored-material billing; it likely adds an unsupported amount or compares the wrong financial base.
Option D: $880,000
$880,000 is above the supported result for stored-material billing; it likely adds an unsupported amount or compares the wrong financial base.
Memory Technique
Retainage and approved live in different drawers; Manager Checks tells which opens.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 10th Edition to Project cost controls; stored-material retainage; verify the construction method, material quantity, equipment use, unit conversion, or field-control calculation.
More Project Mgmt Questions
The field condition is: the work should be released only if the team addresses that thermal movement must be accommodated. Which coping joint detail best matches the condition?
From the mechanical schedule, what CFM is listed for DOAS-2?
From panel schedule R1, what wire size is shown for circuit R1-5?
A subcontractor asks for direction after noting that the work should be released only if the team addresses that subgrade and aggregate must remain separated. Which geotextile selection best fits the work?
From the specialty item schedule, what height is listed for SP-3?
Using the drawing index, which sheet should you open for the entry wall footing plan?
From the plumbing fixture schedule, what waste size is listed for UR-1?
A Ocala task creates flying-particle exposure because a worker is cutting masonry. Which PPE control is required?
From the light fixture schedule, what mount is listed for L1?
From the loading strip dimension plan, what perimeter length is needed for edge restraint?