For a volume-only planning exercise, washout solids total 92 cubic yards before 15% handling allowance. Each approved container has 10 cubic yards usable capacity; weight limits are assumed nonbinding. How many container loads are needed?
Correct Answer
C) 11 containers
92 × 1.15 /10 = 10.58 loads; round up to 11. Actual hauling must also satisfy weight and disposal requirements; this calculation addresses only supplied usable volume.
Why This Is the Correct Answer
92 × 1.15 /10 = 10.58 loads; round up to 11. Actual hauling must also satisfy weight and disposal requirements; this calculation addresses only supplied usable volume.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Project Mgmt Questions
A sloped roof surface measures 7,360 square feet. Add 8% waste and express the result in 100-square-foot roofing squares, to the nearest 0.1 square.
Grinding metal creates flying-particle hazards to a worker’s eyes and face. Which PPE action addresses those hazards?
The project inspection plan requires in-wall rough-in approval before gypsum board conceals stud cavities. Which coordination item must be completed before close-in?
A low-slope roof detail requires base flashing continuous with the field membrane before its upper edge is counterflashed. The membrane-to-wall transition is not yet installed. Which listed step addresses that missing interface?
A membrane takeoff covers 13,720 square feet before 8% waste. Express the adjusted area in 100-square-foot roofing squares, to the nearest 0.1 square.
An office needs carpet tile over 9,975 square feet, plus one combined 15% allowance for waste and spare stock. Each carton supplies 48 square feet. How many whole cartons are needed?
A grout takeoff requires 11.5 cubic feet including its allowance. For this exercise, each bag yields 0.45 cubic foot. How many whole bags are needed?
A steel connection schedule identifies which joints require snug-tight installation and which require pretensioning. Which approach follows that schedule?
A sling’s required safe-working-load identification is illegible before a planned lift. Which action is required?
A supplied metal-deck takeoff calls for 18 approved pins per sheet over 175 sheets. Boxes contain 900 pins. With no additional allowance, how many whole boxes are required?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Related Study Resources
Previous Question
A foundation detail specifies a drainage composite behind the wall connected to a footing drain with a functioning approved outlet and required filtration. Which option maintains that path?
Next Question
Using the supplied practice drawing, in the partition base detail, what material is keynote 36?